Today, We start the work of the third part for laying asphalt concrete, the target is to complete all internal workspaces & roads.

Continue reading

Specialized engineers working now at ASSAIL PLAST factory for installed the internal cooling system of the factory, and
also the installation of electrical systems.
The work includes: Installation, Extend connections, Linking the internal network, Preparation and distribution of
Machinery and processed with the necessary extensions.

Continue reading

After installing the latest equipment, currently being worked on completion of the work of yards and internal asphalt roads of the plant, also ASSAILPLAST going to work on the installation of the external umbrella for the cooling system unite.